Ramsay and Inglewood, Calgary
Ramsay–Inglewood's streetscape is down to its last major phase
The final major Stage 1 work has moved onto 11 Street S.E. A new signal is expected this month, while the last finishing work remains on the spring 2027 calendar.

The long construction season on the Ramsay–Inglewood border has reached a useful milestone. Calgary's newest notice says the project has moved into its final major Stage 1 phase, concentrating work on the west side of 11 Street S.E. between 9 Avenue and 11 Avenue.
That does not make the corridor finished. It does make the remaining sequence easier for residents, businesses and anyone comparing these inner-city neighbourhoods to read: the largest fall work has narrowed to one stretch, a new traffic signal is expected later in October, and the last activities remain scheduled for spring 2027.
Twelve Street is returning to normal operation
The contractor, Aecon, repaired a sanitary issue at 12 Street and 9 Avenue S.E. and resumed major paving. The notice says temporary traffic controls on 12 Street can soon be removed, returning its lanes and intersections to normal operation.
The tradeoff has shifted to 11 Street. A temporary one-way northbound pattern is in effect through the current work zone. Access to 10 Avenue and west-side rear lanes comes from 10 Street, and the rear-lane entrance on 11 Street will be unavailable while that road section is rebuilt. Pedestrian access is to remain open through or around the construction.
The signal is a milestone, not the finish line
The City expects to activate the new traffic signal at 12 Street and 11 Avenue later this month. That is a concrete change to how the corridor functions, but it should not be confused with completion of every sidewalk, landscape or streetscape element.
Crews are continuing sidewalks, curbs, stormwater soil cells, trees, street furniture, bike racks, lighting and road work. Weather permitting, the City aims to finish the major underground and concrete work before the winter shutdown. Remaining activities are expected in spring 2027.
The neighbourhood payoff comes after the detours
Stage 1 is intended to improve the public realm along 11 and 12 streets and support future transit-oriented development. For a household or business considering the area, the immediate consequence is more practical than promotional: check the route you actually use, allow for the one-way section and follow the project map when rear-lane access matters.
The broader Ramsay–Inglewood program still includes later streetscape, underpass and Greenway work that depends on future planning and funding. Today's milestone belongs to the active Stage 1 corridor. It does not establish a construction date for those later pieces, promise a property-value effect or mean every block is already complete.
The next update worth watching is straightforward: confirmation that the new signal is operating and that the fall underground and concrete work has reached the winter shutdown point. Spring 2027 will carry the remaining finish work from there.