Memorial Drive is crossing Stoney Trail. It will not connect to it.

Bridge piling is underway on Calgary's east-side road extension, while the new boulevard, rail crossing and delayed noise barriers remain on a 2027–28 construction sequence.

Real Estate PartnersPublished Nov 1, 20263 min read
Share by emailSend a correction
Conceptual winter construction scene with bridge columns, earthmoving equipment and new communities in the distance beneath the words The East Connection Is Underway.
AI-generated conceptual road-construction scene, not a photograph of the Memorial Drive Extension or an official City rendering.

The gap at the east end of Memorial Drive is no longer only a line on a transportation plan. Calgary's October project update says construction is active on both sides of Stoney Trail, where crews are building the earthworks and foundations for a new overpass.

Roadwork is also continuing on Memorial Drive and Abbeydale Drive into mid-November. Two-way traffic is being maintained through the temporary lane closures, while nearby street parking and pedestrian routes are changing with the work.

A crossing, not another interchange

The four-lane bridge will carry Memorial Drive over Stoney Trail, but it will not add ramps. The City says another interchange would sit too close to the existing connections at 16 Avenue and 17 Avenue, creating unsafe weaving and merging conditions. For future trips between Abbeydale, Applewood Park, Belvedere and the lands farther east, the extension is a continuous east-west route—not a new way onto Stoney.

The design continues east to 84 Street as an urban boulevard, with paths, planned transit stops and lower-speed neighbourhood connections. It also includes an at-grade CN rail crossing with flashing lights, bells, vehicle gates and a protected route for people walking or cycling.

The bridge is ahead of the boulevard

The construction sequence matters. In 2026, the schedule concentrates on the existing westbound roadway, the rail crossing, a west-side storm pond and site preparation for the Stoney Trail and Rotary Mattamy Greenway bridges. The extension roadway itself is shown in the 2027 and 2028 columns.

Bridge foundations, supports and decks are planned for 2027, followed by paving, pathway connections and finishing work in 2028. Calgary currently expects the overall project to finish in 2028. That is the project schedule, not a promise that every segment or connection will open on one fixed day.

The Greenway detour will outlast this season

Piling and embankment work at Stoney Trail is expected to continue into November. A section of the Rotary Mattamy Greenway is detoured for the future bridge and is expected to remain that way until 2028. That makes the construction relevant now even though the through-road benefit is later.

Two noise barriers moved to 2027

The City plans two noise barriers along the north side of Memorial Drive east of Abbeydale Drive after affected properties supported them through the required survey. Their installation was originally part of the 2026 work, but the current update moves it to 2027 because of manufacturing delays.

That delay does not remove the barriers from the design. It does mean nearby households should separate the temporary construction conditions from the eventual road-noise treatment, and follow the project page for the installation schedule rather than assuming the walls arrive with this fall's bridge work.

Road and water work are sharing the corridor

The Memorial project is being coordinated with the East Belvedere feeder main. The water project is installing a two-kilometre line along a similar alignment to serve current and future development, with one eastern phase already complete. Coordinating the routes is meant to avoid reopening the same corridor for work that can be sequenced together.

For an east-Calgary property search, the practical picture has three time frames. There are current lane, parking and pathway changes. There is a multi-year construction corridor. And there is a future connection intended to support growth in Belvedere, Huxley and Twinhills. None of those stages establishes a property-value increase or a guaranteed travel time from a particular home—but the distinction is much more useful than treating the road as either unbuilt or finished.