Two Green Line bridges are ready for the next layer
Blackfoot Trail and 78 Avenue now have substantially complete LRT bridges, but tracks, finishing work and the wider Green Line build still lie ahead.

Two of the first permanent pieces of Calgary's Green Line have crossed a meaningful construction threshold. The City said November 9 that the new LRT bridges over Blackfoot Trail and 78 Avenue S.E. are substantially complete.
That term has a specific limit. Most of the work is finished and the structures are ready for their intended use, while landscaping and other finishing work may continue. It does not mean Green Line trains are about to run: track and the connections to the broader alignment will be installed during later construction.
Blackfoot Trail kept moving beneath the work
The Blackfoot Trail bridge, just south of Crossroads Market, was built over roughly 12 months while traffic continued on the road below. Its concrete deck is designed for future Green Line tracks and a multi-use pathway, giving this early LRT structure a role in both transit and active transportation.
Seven girders now span 78 Avenue
In Ogden, the second bridge runs beside the CPKC railway and the recently completed 78 Avenue underpass. Crews built the foundations, retaining walls and abutments, then installed seven precast concrete girders before pouring the deck that will eventually carry trains over 78 Avenue.
Nearby work should not be swept into the same announcement. The Ogden Road realignment remains a current project with substantial completion anticipated, rather than one of the two structures the City has now confirmed at that stage.
A milestone readers can see—without skipping the stages ahead
For people moving through southeast Calgary, the completed bridge structures make the future alignment easier to read on the ground. They also narrow two active construction files from major structural work to later finishing and integration.
The wider consequence will arrive in layers. Tracks, systems, stations and connections still have to turn these isolated structures into an operating transit line. Substantial completion is real progress; it is not an opening date.